The appropriate selection of training is a guarantee of success. However, the choice is very important, ITCertKing popularity is well known, there is no reason not to choose it. Of course, Give you the the perfect training materials, if you do not fit this information that is still not effective. So before using ITCertKing training materials, you can download some free questions and answers as a trial, so that you can do the most authentic exam preparation. This is why thousands of candidates depends ITCertKing one of the important reason. We provide the best and most affordable, most complete exam training materials to help them pass the exam.
If you are still struggling to prepare for passing PK1-003 certification exam, at this moment ITCertKing can help you solve problem. ITCertKing can provide you training materials with good quality to help you pass the exam, then you will become a good CompTIA PK1-003 certification member. If you have decided to upgrade yourself by passing CompTIA certification PK1-003 exam, then choosing ITCertKing is not wrong. Our ITCertKing promise you that you can pass your first time to participate in the CompTIA certification PK1-003 exam and get CompTIA PK1-003 certification to enhance and change yourself.
ITCertKing's practice questions and answers about the CompTIA certification PK1-003 exam is developed by our expert team's wealth of knowledge and experience, and can fully meet the demand of CompTIA certification PK1-003 exam's candidates. From related websites or books, you might also see some of the training materials, but ITCertKing's information about CompTIA certification PK1-003 exam is the most comprehensive, and can give you the best protection. Candidates who participate in the CompTIA certification PK1-003 exam should select exam practice questions and answers of ITCertKing, because ITCertKing is the best choice for you.
Wanting to upgrade yourself, are there plans to take CompTIA PK1-003 exam? If you want to attend PK1-003 exam, what should you do to prepare for the exam? Maybe you have found the reference materials that suit you. And then are what materials your worthwhile option? Do you have chosen ITCertKing CompTIA PK1-003 real questions and answers? If so, you don't need to worry about the problem that can't pass the exam.
Let me be clear here a core value problem of ITCertKing. All CompTIA exams are very important. In this era of rapid development of information technology, ITCertKing just one of the questions providers. Why do most people to choose ITCertKing ? Because the ITCertKing exam information will be able to help you pass the test. It provides the information which is up to date. With ITCertKing CompTIA PK1-003 test questions, you will become full of confidence and not have to worry about the exam. However, it lets you get certified effortlessly.
Exam Code: PK1-003
Exam Name: CompTIA (CompTIA Project+ Beta Exam)
One year free update, No help, Full refund!
Total Q&A: 240 Questions and Answers
Last Update: 2014-02-09
There a galaxy of talents in the 21st century, but professional IT talents not so many. Society need a large number of professional IT talents. Now IT certification exam is one of the methods to inspect the employees' ability, but it is not so easy to is one of the way to IT certification exams. Generally, people who participate in the IT certification exam should choose a specific training course, and so choosing a good training course is the guarantee of success. ITCertKing's training course has a high quality, which its practice questions have 95% similarity with real examination. If you use ITCertKing's product to do some simulation test, you can 100% pass your first time to attend IT certification exam.
PK1-003 Free Demo Download: http://www.itcertking.com/PK1-003_exam.html
NO.1 A project manager reports directly to the project management office of a company. All project team
members report to a functional manager; however, all the team members work assignments are made by
the project manager. Which of the following types of organizational structures does this represent?
A. Weak Matrix
B. Functional
C. Strong Matrix
D. Projectized
Answer: C
CompTIA answers real questions PK1-003 braindump PK1-003 study guide PK1-003 PK1-003 exam dumps
NO.2 Which of the following BEST describes the critical path of a project?
A. A modified version of a project schedule taking into account limited resources and external
dependencies.
B. The length of time between the two most critical milestones of a project.
C. The shortest possible path through a project, represented by the sum of the duration of all scheduled
activities, with zero float.
D. A PDM network diagram illustrating, in detail, all mandatory, discretionary and external dependencies
for a given project.
Answer: C
CompTIA PK1-003 questions PK1-003
NO.3 Which of the following should be created in the project closing documentation? (Select TWO).
A. Closure report summarizing costs
B. Responsibility assessment matrix
C. Lessons learned
D. Project timeline
E. Statement of Work (SOW)
Answer: AC
CompTIA PK1-003 pdf PK1-003 demo PK1-003 test questions PK1-003
NO.4 Who has the MOST influence over project decisions?
A. Project team members
B. End users
C. Key stakeholders
D. Project manager
Answer: C
CompTIA test answers PK1-003 PK1-003 PK1-003 exam simulations PK1-003 practice test PK1-003 dumps
NO.5 During a project status meeting a positive project risk is identified and is within the teams control.
Which of the following would be the BEST response?
A. Accept the risk.
B. Transfer the risk.
C. Mitigate the risk.
D. Exploit the risk.
Answer: D
CompTIA PK1-003 test PK1-003 dumps PK1-003 test
NO.6 Several key resources will be unavailable at the end of the project. The key stakeholders want to
outsource the project to a third party. Which of the following risk responses is described in this situation?
A. Risk avoidance
B. Risk mitigation
C. Risk acceptance
D. Risk transference
Answer: D
CompTIA PK1-003 PK1-003 practice test PK1-003 practice test PK1-003 practice test
NO.7 Which of the following are required to complete the pre-project setup? (Select THREE).
A. Completion of approved change control documents
B. Preparation of the project charter
C. Completion of the work breakdown structure (WBS)
D. Obtaining final approval of the project charter
E. Validation of the project
F. Completion of the key performance indicators (KPIs)
Answer: BDE
CompTIA PK1-003 original questions PK1-003 practice test PK1-003 pdf
NO.8 Which of the following risk response strategies involves shifting the negative impact of a threat, along
with ownership of the response, to a third party?
A. Risk transfer
B. Risk avoidance
C. Risk sharing
D. Risk mitigation
Answer: A
CompTIA PK1-003 practice test PK1-003 PK1-003 questions
NO.9 A project team is comfortable working as a group and has accepted all the project ground rules. They
support each other to reach the project goals. Which of the following stages of team development is the
project team demonstrating?
A. Storming
B. Performing
C. Conforming
D. Forming
Answer: B
CompTIA PK1-003 PK1-003
NO.10 A customer does not have the staff available to complete a particular project, but anticipates that more
staff will be hired in the future. While the project budget has been established, the project scope has not.
Which of the following is the BEST action for the project manager to take?
A. Start the project immediately because the funding is available.
B. Start the important project; the project manager can define the scope.
C. Do not start the project because the customer has not provided enough resources.
D. Do not start the project until the scope has been clearly defined.
Answer: D
CompTIA braindump PK1-003 certification training PK1-003 dumps
NO.11 Which of the following would be a direct output of the initiating process group? (Select TWO).
A. Project charter
B. Project management plan
C. Statement of Work (SOW)
D. Work Breakdown Structure (WBS)
E. Preliminary scope statement
Answer: AE
CompTIA PK1-003 PK1-003 PK1-003 original questions
NO.12 In which of the following organization types is it LEAST likely that a conflict regarding competing
demands for resources would take place?
A. Functional
B. Weak Matrix
C. Balanced Matrix
D. Projectized
Answer: D
CompTIA PK1-003 braindump PK1-003 PK1-003 PK1-003 certification training
NO.13 Design, launch, review and test are examples of which of the following work breakdown structure (WBS)
schemes?
A. Functions
B. Organizational units
C. Product components
D. Geographical areas
Answer: A
CompTIA exam prep PK1-003 PK1-003 PK1-003 practice test
NO.14 Which of the following quality control tools illustrates the various factors that may be linked to potential
problems or effects?
A. Ishikawa diagram
B. Histogram
C. Run chart
D. Scatter diagram
Answer: A
CompTIA questions PK1-003 PK1-003 pdf PK1-003 PK1-003 dumps
NO.15 Which of the following are process groups in the project life cycle? (Select THREE).
A. Accepting
B. Mitigating
C. Avoiding
D. Initiating
E. Closing
F. Planning
Answer: DEF
CompTIA test PK1-003 PK1-003
NO.16 Which of the following describes the LOWEST level of a work breakdown structure (WBS)?
A. Technical specifications
B. Project performance reports
C. Work packages
D. Functional specifications
Answer: C
CompTIA PK1-003 PK1-003 PK1-003 original questions
NO.17 A purpose of formal project closure is to:
A. assess blame for the failure of the project.
B. provide lessons learned for future projects.
C. start a new project.
D. outline the responsibilities of each team member.
Answer: B
CompTIA PK1-003 exam PK1-003 original questions PK1-003
NO.18 A project manager is in a projectized organization managing a particular project. A department manager
has repeatedly requested a change to the scope of the project which was previously denied. The project
is currently behind schedule. Which of the following would be the BEST way to deal with the managers
repeated request?
A. Request the manager fill out a formal request for the change and file it with the project management
office.
B. Have a team member meet with the manager so the project can stay on schedule.
C. Ask the project sponsor to respond to the department manager.
D. Implement the change as requested by the manager and inform the project sponsor.
Answer: C
CompTIA exam prep PK1-003 test PK1-003 exam simulations PK1-003 questions PK1-003
NO.19 Which of the following activities would happen LAST in procurement management?
A. Request seller responses
B. Perform contract administration
C. Perform vendor selection
D. Perform a make or buy analysis
Answer: B
CompTIA PK1-003 practice test PK1-003 demo PK1-003
NO.20 A project manager is presented with a change request for an ongoing project. Which of the following
would be the FIRST action?
A. Update the project plan to accommodate the changes.
B. Perform an impact analysis.
C. Organize a stakeholder meeting to review the changes.
D. Change the project scope to reflect the change request.
Answer: B
CompTIA PK1-003 questions PK1-003
NO.21 A project manager receives a request for a minor change to one of the deliverables. Which of the
following documents would MOST likely be impacted?
A. Work Breakdown Structure (WBS)
B. Project charter
C. Communication plan
D. Quality plan
Answer: A
CompTIA PK1-003 PK1-003 braindump PK1-003
NO.22 A project budget has been reduced by 10 percent, but the project has a critical deadline. Which of the
following should the project manager do FIRST to complete the project on time?
A. Lower the quality standards for the finished product.
B. Analyze the impact of the change.
C. Eliminate 10 percent of the projects resources.
D. Document the approved change request.
Answer: B
CompTIA answers real questions PK1-003 PK1-003 PK1-003 exam simulations
NO.23 Which of the following describes a qualitative risk analysis tool that assigns ratings to project risk
factors based upon the likelihood of occurrence and the affect it will have on the project?
A. Cause and effect diagram
B. Risk register
C. Probability and impact matrix
D. Decision tree analysis
Answer: C
CompTIA PK1-003 PK1-003 original questions PK1-003 PK1-003
NO.24 Which of the following would MOST likely be included in a project scope document?
A. WBS
B. Quality metrics
C. Risk responses
D. KPIs
Answer: D
CompTIA exam PK1-003 PK1-003 questions PK1-003
NO.25 Which of the following tools is the BEST to measure data organized in time sequence?
A. Run chart
B. Ishikawa diagram
C. Pareto chart
D. Histogram
Answer: A
CompTIA test PK1-003 PK1-003 PK1-003 PK1-003 PK1-003 pdf
NO.26 The communication plan for a project is a subset of which of the following documents?
A. Project charter
B. Risk management plan
C. Project schedule
D. Project plan
Answer: D
CompTIA PK1-003 braindump PK1-003 PK1-003 dumps
NO.27 Which of the following tools are used for quality planning? (Select TWO).
A. Cost / Benefit analysis
B. Network diagram
C. Benchmarking
D. Critical Path Method (CPM)
E. Parametric estimating
Answer: AC
CompTIA dumps PK1-003 PK1-003 PK1-003 PK1-003
NO.28 Which of the following is the purpose of a Pareto diagram?
A. To show the sequence in which work will be performed
B. To create the process that will complete the project
C. To determine the critical path
D. To direct team efforts to the areas that will have the most impact
Answer: D
CompTIA certification PK1-003 practice test PK1-003
NO.29 Two of the stakeholders cannot agree on the project timeline or budget. The project is critical to the
success of the company. Which of the following actions should the project manager take NEXT?
A. Invite all of the stakeholders to a meeting to discuss project requirements.
B. Document the points of agreement and create the timeline and budget based upon the expectations of
the majority of the stakeholders.
C. Modify the project scope to bring it into alignment with the stakeholders expectations.
D. Inform the stakeholders that the project will be cancelled if they cannot agree.
Answer: A
CompTIA test PK1-003 PK1-003 exam prep PK1-003
NO.30 A project manager is two weeks into a project when an unexpected delay occurs. Material that is
needed to complete the project could be available in three business days; however, the project team
believes that estimate is unrealistic and that it will take five business days for the material to arrive. The
project manager was informed by another employee in the material company that it could take up to
thirteen days to receive the materials. Which of the following estimates should be given to the project
sponsor?
A. 5 business days
B. 6 business days
C. 8 business days
D. 13 business daysb
Answer: B
CompTIA certification training PK1-003 PK1-003 exam
ITCertKing offer the latest 000-N55 exam material and high-quality 050-SEPROGRC-01 pdf questions & answers. Our FCNSA.v5 VCE testing engine and HP0-S34 study guide can help you pass the real exam. High-quality 70-462 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.
Article Link: http://www.itcertking.com/PK1-003_exam.html